Athanor
Market detailInstant. You clear the sell orders and start the job today.
Cheaper, but you wait for the fills — and the bid can move while you do.
The fee is charged on the job’s Estimated Item Value — the blueprint’s ME0 quantities priced at CCP’s adjusted prices — not on what the materials cost you. A researched blueprint cuts your material bill and leaves this number completely unchanged. Where you install the job is the lever that moves it.
Fee profile: Omega trader. Sales tax always applies; the broker fee is charged because the realistic exit is a sell order at the ask, not dumping the run into buy orders.
| Material | Base / run | Units / job | Jita ask | Jita bid | Line @ ask | Line @ bid | EIV basis |
|---|---|---|---|---|---|---|---|
| Structure Acceleration Coils | 1 | 1 | 149,000,000 | 76,500,000 | 149,000,000 | 76,500,000 | 122,073,807.37 |
| Structure Construction Parts | 1 | 1 | 44,980,000 | 30,290,000 | 44,980,000 | 30,290,000 | 18,435,545.63 |
| Structure Docking Bay | 1 | 1 | 54,800,000 | 32,330,000 | 54,800,000 | 32,330,000 | 6,581,971.55 |
| Structure Electromagnetic Sensor | 1 | 1 | 182,500,000 | 81,700,000 | 182,500,000 | 81,700,000 | 43,887,759.76 |
| Structure Hangar Array | 1 | 1 | 53,950,000 | 30,300,000 | 53,950,000 | 30,300,000 | 58,885,251.83 |
| Structure Repair Facility | 1 | 1 | 57,890,000 | 30,300,000 | 57,890,000 | 30,300,000 | 53,612,045.46 |
| Structure Reprocessing Plant | 3 | 3 | 73,970,000 | 57,380,000 | 221,910,000 | 172,140,000 | 64,528,485.33 |
| Structure Storage Bay | 1 | 1 | 55,000,000 | 32,750,000 | 55,000,000 | 32,750,000 | 44,774,674.93 |
| Materials, whole job | 820,030,000 | 486,310,000 | 541,836,512.52 | ||||
EIV basis is CCP’s published adjusted price. It exists to compute the install fee and nothing else — nobody sells at it, so it is never used as a cost here.
- Material efficiency 10 and 1 run. ME is applied to the whole job and rounded once, never per run, and no material ever drops below one unit per run.
- Installed in Jita, manufacturing cost index 17.23%. Facility tax 0.25%, SCC surcharge 4%.
- Materials and the finished item are priced from the live Jita book (The Forge). The install fee is computed from CCP’s adjusted prices, which are an index, not a quote.
- Sale assumes a sell order at the current Jita ask, paying 2.02% sales tax and 1.50% broker fee (Omega trader). No hauling, no time cost, no blueprint cost.
- 30-day Jita context: 9.8 trades/day, 11 units/day.